Application for payment UK: how to value and submit
An application for payment (AFP) claims the cumulative value of work completed to a valuation date. Unlike a VAT invoice, it starts the contract certification timetable rather than creating an immediate VAT tax point.
This guide shows UK subcontractors how to structure, evidence and submit applications. It is general information only, not legal or tax advice. Check your contract on disputes.
What an application for payment must show
State the sum due and basis of calculation. Under section 110B(4) of the 1996 Act, a compliant contractual application becomes the default notice if the payer serves none.
Put every cumulative line on one summary sheet:
- Job and valuation ref: Subcontract number, period and date.
- Original contract sum: Tender total by schedule of values.
- Gross work to date: Cumulative measured progress per line.
- Variations: Itemised additions and omissions, agreed vs pending.
- Materials on site: Only where the contract permits with title proof.
- Less retention: Contractual percentage deducted from gross cumulative value.
- Less previous certified sums: Earlier totals, giving net sum applied for.
- CIS and VAT note: CIS status and reverse-charge note for invoicing.
Valuation dates, due dates and final date for payment
Under section 109 of the 1996 Act, qualifying contracts in England, Wales and Scotland carry stage-payment rights unless work is agreed under 45 days.
Section 110 requires an adequate payment mechanism and final payment date. Parties agree intervals and periods. Payment cannot depend on performance under another contract (section 110(1A)) or on a payment notice being given (section 110(1D)).
Where an England or Wales contract omits compliant dates, Scheme 1998 Part II implies defaults:
- Valuation period: 28 days (paragraph 12).
- Interim due date: Later of 7 days post-period or claim (paragraph 4).
- Final due date: Later of 30 days post-completion or claim (paragraph 5).
- Final date for payment: 17 days from due date (paragraph 8).
Under HMRC VAT Notice 708 (paragraph 23.1.3), the periodic VAT tax point is payment receipt or VAT invoice issue, whichever comes first. Label claims "Application for Payment", not VAT invoice.
Evidence pack to attach to every valuation
Attach one indexed pack behind your summary:
- Marked-up drawings showing installed quantities.
- Signed variation instructions, build-ups and weekly daywork sheets.
- Delivery notes and vesting certificates for materials on site.
- Dated progress photos for concealed works.
- CIS verification details and reverse-charge wording.
Worked example: Cedar Mews valuation 4 (fictional)
On fictional Cedar Mews (GBP 120,000.00 M&E subcontract, 5% retention), Valuation 4 runs at month four.
| Valuation line | Cumulative (GBP) |
|---|---|
| Measured contract works (65%) | 78,000.00 |
| Agreed variations (VAR-01 to VAR-04) | 6,000.00 |
| Gross cumulative valuation | 84,000.00 |
| Less 5% retention | -4,200.00 |
| Net cumulative valuation | 79,800.00 |
| Less previous certified payments (Valuations 1 to 3) | -51,300.00 |
| Net sum applied for (Valuation 4, ex VAT) | 28,500.00 |
The sheet states GBP 28,500.00 net due and shows every line's calculation basis.
Common mistakes that delay certification
- Missing cut-off dates. Submitting late defers payment by a month.
- Claiming monthly increments. Non-cumulative totals break retention checks.
- Sending an early VAT invoice. Invoicing early triggers output VAT early.
- Omitting the calculation basis. Bare totals fail sections 110A and 110B.
- Using the wrong portal or email. Follow the service clause strictly.
How this looks in Lode
Lode compares agreed scope with site notes, revised drawings and supplier bills. It drafts priced variations and flags unbilled work with supporting records beside the job.
Your commercial manager prepares the valuation and checks retention. Someone on your team approves each one before it goes out.
Related guides
- UK payment and pay less notices
- UK construction variations
- Construction retention release UK
- CIS and VAT reverse charge UK
- Building contractors
Book a walkthrough
Book a walkthrough to see Lode price variations and check supplier bills on sample data.
Sources
These primary statutory and HMRC sources cover UK construction payment dates and periodic VAT tax points. This guide is general information only, not legal, quantity surveying or tax advice.
- Housing Grants, Construction and Regeneration Act 1996, Part II (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/part/II
- Local Democracy, Economic Development and Construction Act 2009, Part 8 (2026-11-23): https://www.legislation.gov.uk/ukpga/2009/20/part/8
- The Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II (2026-11-23): https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II
- HMRC Buildings and construction, VAT Notice 708 (2026-11-23): https://www.gov.uk/guidance/buildings-and-construction-vat-notice-708