Guide
UK payment notices and pay less notices: rules and deadlines
Under the UK Construction Act (1996 Act Part II, amended by the 2009 Act), a payer must pay the notified sum by the final date. The main exception is serving a valid pay less notice on time.
This guide covers statutory notice dates and suspension rights in England, Wales and Scotland. Defaults follow the England and Wales Scheme 1998; Scotland uses separate regulations. This page is general information only, not legal advice.
The statutory payment timeline
Every qualifying contract must set a payment due date and a final date for payment:
- Payment notice (s.110A): Served within 5 days after the due date by the contract's named party.
- Notified sum (s.111(1)): The valid notice sum becomes payable on or before the final date.
- Pay less notice (s.111(3)-(5)): Served before the prescribed period prior to the final date. England and Wales Scheme paragraph 10 defaults to 7 days before the final date.
Where a contract omits a final date, Scheme paragraph 8 implies 17 days after due date. Under section 116, periods start the day after the trigger and exclude Christmas Day, Good Friday and bank holidays.
What makes a payment notice or pay less notice valid
Under sections 110A and 111, every notice must state two items:
- Sum considered due: At the due date (payment notice) or service date (pay less notice). Zero can still be valid.
- Basis of calculation: A clear build-up explaining the figure, not a bare total.
Follow the contract's service clause for email, portal and cut-off times. Without agreement, section 115 allows written service by any effective means. Under section 111(5)(b), a pay less notice cannot precede a payee or default notice.
Default payment notices and the right to suspend
Where a payer or specified person misses the 5-day payment notice deadline, section 110B applies:
- Payee default notice (s.110B(2)-(3)): Serve your own notice after the missed deadline. The final date moves back by the same days.
- Application as default notice (s.110B(4)): A compliant advance application for payment under the contract becomes the default notice automatically. You cannot serve another.
- Right to suspend (s.112): If unpaid past the final date, you may suspend any or all work. First give at least 7 days' written notice stating grounds. Sections 112(3A) and 112(4) cover reasonable costs and time extensions.
Worked timeline: Cedar Mews (fictional)
This fictional October 2026 schedule uses England and Wales Scheme defaults (no October bank holidays) for Valuation 4 (GBP 28,500.00).
| Milestone | Date (2026) | Basis |
|---|---|---|
| Period ends | Fri 2 Oct | 28-day period (Scheme para 12) |
| Application sent | Mon 5 Oct | Written claim, GBP 28,500.00 |
| Payment due date | Fri 9 Oct | Later of +7d post-period or claim (para 4) |
| Payment notice cutoff | Wed 14 Oct | 5 days after due date (s.110A / para 9) |
| Pay less cutoff | Mon 19 Oct | 7 days before final date (s.111 / para 10) |
| Final date for payment | Mon 26 Oct | 17 days after due date (para 8) |
| Notice to suspend | Tue 27 Oct | At least 7 days' written notice (s.112) |
| Earliest suspension | Wed 4 Nov | After 7 clear days (s.112, s.116(2)) |
A valid 19 October pay less notice cutting payment to GBP 27,000.00 sets GBP 27,000.00 due on 26 October. Without one, GBP 28,500.00 stays due.
Records to keep when a notice is late or disputed
- Timestamped proof of sending your application.
- Signed payment schedule, amendments and service rules.
- Every incoming notice with date and time received.
- Calculation sheet and supporting variation records.
- Dated chase log and written notices before suspending.
How this looks in Lode
Lode flags finished work with no invoice and overdue payments. It drafts the payment follow-up with the quote, variations and invoice history beside it.
Your director or commercial lead checks contract dates and figures. Someone on your team approves each one before it goes out.
Related guides
- Application for payment UK
- Construction retention release UK
- UK construction variations
- Building services (MEP) and Building contractors
Book a walkthrough
Book a walkthrough to see Lode flag overdue payments and draft a follow-up with supporting records on sample data.
Sources
These primary statutory sources cover payment notices, default notices, pay less notices and suspension rights. This guide is general information only, not legal advice.
- Housing Grants, Construction and Regeneration Act 1996, Section 110A (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/section/110A
- Housing Grants, Construction and Regeneration Act 1996, Section 110B (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/section/110B
- Housing Grants, Construction and Regeneration Act 1996, Section 111 (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/section/111n1
- Housing Grants, Construction and Regeneration Act 1996, Section 112 (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/section/112
- Housing Grants, Construction and Regeneration Act 1996, Section 115 (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/section/115
- Housing Grants, Construction and Regeneration Act 1996, Section 116 (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/section/116
- The Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II (2026-11-23): https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II