Construction retention release UK: tracking and recovery

By Lode

Construction retention holds back a percentage of contract value against defects or insolvency. Customarily, half releases at project completion and half after the defects liability period.

This guide shows UK contractors how to track retention, build release packs and protect recovery dates. It is general information only, not legal or tax advice. Check your signed contract on disputes.

Why retention cash goes uncollected

Government figures put retentions at 3% to 5% against 1% to 2% average profit margins. Cash goes unclaimed for four reasons:

  • Long defects periods. A 12-month or 24-month window outlasts the project team.
  • Staff turnover. Once a contractor's QS leaves, nobody releases cash without a written claim.
  • Unclosed snags and missing manuals. One missing certificate lets the payer hold the final half.
  • No written claim. Contracts require formal claims at practical completion and defects end.

Watch clauses tying release to the main contract certificate. Under section 110(1A) of the 1996 Act, payment cannot depend on another contract. Under section 113, "pay when paid" clauses are ineffective except in third-party insolvency.

The retention ledger: fields to track on every job

Review one central retention ledger across live and completed subcontracts monthly.

Ledger fieldWhat to recordCheck
JobProject name and subcontract refLinks job file
Client / main contractorLegal entity, accounts, QSRoutes claim
Retention percentageAgreed rate (typically 3% to 5%)Matches contract
Gross certifiedCumulative certified valueMatches notice
Retention heldTotal GBP deductedMatches ledger
Practical completion dateSigned handover dateStarts first clock
First moiety due / claimedTarget date, sum, claim dateChecks notice
Defects period endRectification expiry dateDiarise -30 days
Final moiety due / claimedTarget date, sum, claim dateChase if late
StatusOpen, PC claimed, Defects, PaidFlags overdue

Preparing the release pack at practical completion and defects end

Gather close-out records while crews remain on site:

  • Practical completion pack: Handover certificate, commissioning sheets, test certificates, as-built drawings, O&M manuals and a written application for payment.
  • Defects-end pack: Signed snag sheets, repair photos, confirmation of zero open defects and your final claim.

Serve packs by the contract method and keep proof of delivery.

Worked example: Cedar Mews retention schedule (fictional)

On fictional Cedar Mews (GBP 120,000.00 final value, 5% retention, 12-month defects period), release runs across two dates:

MilestoneDateRateReleased (GBP)Held (GBP)
Works complete15 Jan 20275.0%0.006,000.00
Practical completion (first moiety)15 Jan 20272.5%3,000.003,000.00
Defects end (final moiety)15 Jan 20282.5%3,000.000.00

A December 2027 snag check clears open items so the GBP 3,000.00 final claim lands on 15 January 2028.

Retention, payment notices and tax timing

Retention release follows the contract's payment notice and pay less notice timetable under the 1996 Act and 1998 Scheme.

Under HMRC VAT Notice 708 (paragraphs 2.1.1 and 23.1.2), retention takes the same VAT rate as earlier payments. Its VAT tax point waits until receipt of payment or VAT invoice issue, whichever comes first. Confirm VAT and CIS timing with your accountant and read our CIS and VAT reverse charge guide. Large UK companies and LLPs must also publish statutory payment practice reports.

How this looks in Lode

On completion, Lode flags outstanding records and finished work with no invoice for review. For overdue invoices, it drafts the follow-up with invoice history beside it.

Your commercial lead checks retention dates, snags and sums. Someone on your team approves each one before it goes out.

Book a walkthrough

Book a walkthrough to see Lode flag outstanding completion records on sample data.

Sources

These primary statutory and government sources cover construction payment rules, retention VAT tax points and UK payment-practice reporting. This guide is general information only, not legal, quantity surveying or tax advice.

  1. Housing Grants, Construction and Regeneration Act 1996, Part II (2026-11-23): https://www.legislation.gov.uk/ukpga/1996/53/part/II
  2. The Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II (2026-11-23): https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II
  3. HMRC Buildings and construction, VAT Notice 708 (2026-11-23): https://www.gov.uk/guidance/buildings-and-construction-vat-notice-708
  4. UK Government Business payment practices and performance: reporting requirements (2026-11-23): https://www.gov.uk/government/publications/business-payment-practices-and-performance-reporting-requirements
  5. UK Department for Business and Trade, Late payments consultation: tackling poor payment practices (Measure 8, 2026-11-23): https://www.gov.uk/government/consultations/late-payments-tackling-poor-payment-practices/late-payments-consultation-tackling-poor-payment-practices