Construction change order template (Word, PDF and log)

Put every change to the contract on one signed form, then track them all in one log. Download the change order template in Word, the printable PDF or the change order log in CSV. No account is needed.

This template is general information only, not legal advice. Check your contract and local requirements, because many contracts set their own form and notice period.

What the change order form covers

The Word and PDF forms hold the same one-page layout.

  • Project. Change order number, date, project, contract reference, owner, contractor and who asked for the change.
  • Description of change. The work added, removed or changed, with its location.
  • Reason for change. Owner request, unforeseen site condition, design or drawing revision, code or inspection requirement, or other.
  • Supporting documents. The drawing revision, RFI, written instruction, photos or supplier quote behind the change.
  • Cost of this change. Labor, materials, equipment, subcontractor, overhead and profit, and the total to add or deduct.
  • Contract sum. The original sum, earlier change orders, this change order and the new contract sum.
  • Schedule. Days added or removed and the new completion date.
  • Approval. Name, signature and date for the contractor, the owner and the architect or engineer if required.

How to fill it in

  1. Number the change order and name the contract it amends.
  2. Describe the change so a person who was not on site can price it.
  3. Attach the evidence: the instruction, the revised drawing, the RFI answer or the photos.
  4. Price each cost line, then add overhead and profit at the rate your contract allows.
  5. Restate the contract sum and the completion date after this change.
  6. Seek signed approval before the changed work starts, where your contract and the circumstances allow.

Columns in the change order log

The CSV opens in Excel or Google Sheets with nineteen columns.

  • CO_Number, Date_Raised and Project: the change order number, the date raised and the job.
  • Requested_By, Source_Document, Description and Reason: who asked, the evidence and what changed.
  • Labor_USD, Materials_USD, Equipment_USD and Subcontractor_USD: the cost lines.
  • Markup_Pct and Amount_USD: overhead and profit, and the priced amount.
  • Schedule_Days: days added or removed.
  • Status, Approved_By and Date_Approved: where the change stands and who signed it.
  • Invoice_Ref and Notes: the invoice that billed it and the audit notes.

Work out each amount this way.

Amount_USD = (Labor_USD + Materials_USD + Equipment_USD + Subcontractor_USD) x (1 + Markup_Pct / 100)

Use three statuses: approved, pending and rejected. Count only approved lines in the revised contract sum. Keep rejected lines for the record.

Fictional sample log (Cedar Mews)

Four fictional Cedar Mews rows are in the CSV download.

CO_NumberCost lines (USD)MarkupAmount (USD)Status
CO-0011,200.00 labor + 850.00 materials15%2,357.50approved
CO-002640.00 labor + 310.00 materials + 150.00 equipment15%1,265.00pending
CO-0033,000.00 subcontractor10%3,300.00rejected
CO-004400.00 materials deducted0%-400.00approved

Totals: Approved USD 1,957.50, Pending USD 1,265.00, Rejected USD 3,300.00.

An approved line with an empty Invoice_Ref is work you have done and not billed.